CSRR GIS Deliverables
CSRR Regulations, specifically Administrative Requirements for the Remediation of Contaminated Sites [pdf] (ARRCS Rule) (N.J.A.C 7:26C-1.6) and the Technical Requirements for Site Remediation [pdf] (N.J.A.C. 7:26E), require the submittal of GIS compatible maps for several key elements of the remedial investigation / remediation. The Regulations require the submission of GIS deliverables throughout the investigation and remediation of contaminated sites.
Prior to submitting any GIS deliverables to CSRR, please review the following:
- Administrative Requirements for GIS Deliverables [pdf]
- Minimum Accuracy Requirements for GIS Submissions [pdf]
- FAQs
CSRR receives these GIS deliverables via email at specifically designated email addresses or through the online service as specified in the guidance document links below. The GIS deliverables are:
General Site Information | |
---|---|
Submission Type: | Areas of Concern / Site Boundaries [pdf] |
Deliverable: | Polygon |
Key Document: | PA / SI / RI |
Submission Type: | Site Location [pdf] |
Deliverable: | Single Point (Email) |
Key Document: | n/a |
Institutional Control | |
---|---|
Submission Type: | Classification Exception Area (CEA) [pdf] |
Deliverable: | Polygon |
Key Document: | RIR or GW RA Permit Application |
Submission Type: | Deed Notice / Engineering Controls [pdf] |
Deliverable: | Polygon |
Key Document: | Soil RA Permit Application |
Immediate Environmental Concern (IEC) | |
---|---|
Submission Type: | Currently Known Extent (CKE) [pdf] – Potable Well IEC Only |
Deliverable: | Polygon |
Key Document: | Engineered Response Action Report, IEC Source Control (SC) Report, or IEC Response Action Report |
Receptor Evaluation (ground water) | |
---|---|
Submission Type: | Well Search [pdf] |
Deliverable: | Multiple Points (Spreadsheet) |
Key Document: | Initial – 120 days after GW contamination detected Additional – IEC SC Report, RI, RA |
Linear Construction | |
---|---|
Submission Type: | Linear Construction [pdf] |
Deliverable: | Polygons |
Key Document: | Linear Construction Report |
Note: Polygons must be submitted as an Esri polygon shapefile or CAD dwg file.