Annual Site Remediation Reform Act Program Fee Calculation Report
Pursuant to the Administrative Requirements for the Remediation of Contaminated Sites (ARRCS, N.J.A.C. 7:26C), the New Jersey Department of Environmental Protection is to prepare each year an “Annual Site Remediation Reform Act Program Fee Calculation Report.”
The report is to include the information contained in the annual budget submission to the Department of the Treasury, the numbers of contaminated areas of concern and of contaminated media, the base contaminated area of concern fee, the contaminated area of concern fee for each of the four categories, and the contaminated media fee that shall be due and payable. Additionally, the report is to include the factors used to calculate the remedial action permit fee for each remedial action permit activity, as well as the annual remedial action permit fee for each type of Remedial Action Permit. A notice is to be published in the New Jersey Register that includes a summary of the report and its Site Remediation Reform Act Program budget, and the Department is also required to post the report on its website.
The notice regarding the “Annual Site Remediation Reform Act Program Fee Calculation Report” was published in the Monday, June 3, 2024 New Jersey Register. The report is available here Annual Fee Calculation Report .
Implementation of the new fees will be as follows:
- For Annual Remediation Fees, if the invoice sent by the Department is dated:
- On or before June 30, 2024, the Annual Remediation Fees listed in the June 5, 2023 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- On or after July 1, 2024, the Annual Remediation Fees described in the June 3, 2024 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- For Remedial Action Permit Annual Fees, if the invoice sent by the Department is dated:
- On or before June 30, 2024, the Remedial Action Permit Annual Fees listed in the June 5, 2023 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- On or after July 1, 2024, the Remedial Action Permit Annual Fees described in the June 3, 2024 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- For the Remedial Action Permit Activity Fees, if the permit activity (application, modification, transfer, termination) is administratively complete and is post-marked:
- On or before June 30, 2024, the Remedial Action Permit Activity Fees listed in the June 5, 2023 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- On or after July 1, 2024, the Remedial Action Permit Activity Fees described in the June 3, 2024 version of the “Annual Site Remediation Reform Act Program Fee Calculation Report” apply
- For cases that received a limited restricted use or restricted use No Further Action letter from the Department and have not yet applied for and received a remedial action permit, additional information is available at Post-No Further Action Compliance Notice for Cases Requiring a Remedial Action Permit.
Comparison of Fiscal Year 2024 Fees with Fiscal Year 2025 Fees
Annual Remediation Fees
Comparison of FY 2024 and FY 2025 Annual Remediation Fees | |||
---|---|---|---|
Category | FY 2024 Fee | FY 2025 Fee | Difference in Fee Between FY 2024 and FY 2025 |
1 | $925 | $950 | $25 |
2 | $1,850 | $1,900 | $50 |
3 | $10,175 | $10,450 | $275 |
4 | $20,350 | $20,900 | $550 |
Contaminated media | $1,570 | $1,600 | $30 |
Remedial Action Permit Activity Fees
Comparison of FY 2024 and FY 2025 Remedial Action Permit Activity Fees | |||
---|---|---|---|
Remedial Action Permit Activity | FY 2024 Fee | FY 2025 Fee | Difference in Fee Between FY 2024 and FY 2025 |
Soil Remedial Action Permits | |||
Remedial Action Permit Application | $1,430 | $1,380 | ($50) |
Remedial Action Permit Modification | $1,320 | $1,380 | $60 |
Remedial Action Permit Transfer | $550 | $345 | ($205) |
Remedial Action Permit Termination | $1,100 | $1,150 | ($50) |
Ground Water – Natural Attenuation Remedial Action Permits | |||
Remedial Action Permit Application | $880 | $805 | ($75) |
Remedial Action Permit Modification | $880 | $690 | ($190) |
Remedial Action Permit Transfer | $440 | $345 | ($95) |
Remedial Action Permit Termination | $550 | $575 | $25 |
Ground Water – Active System Remedial Action Permits | |||
Remedial Action Permit Application | $880 | $805 | ($75) |
Remedial Action Permit Modification | $880 | $690 | ($190) |
Remedial Action Permit Transfer | $440 | $345 | ($95) |
Remedial Action Permit Termination | $550 | $575 | $25 |
Remedial Action Permit Annual Fees
Comparison of FY 2024 and FY 2025 Remedial Action Permit Annual Fees | |||
---|---|---|---|
Type of Permit | FY 2024 Fee | FY 2025 Fee | Difference in Fee Between FY 2024 and FY 2025 |
Soil Remedial Action Permit | |||
With deed notice without engineering controls | $660 | $575 | ($85) |
With deed notice with engineering controls | $550 | $575 | $25 |
Ground Water Remedial Action Permit | |||
Natural Attenuation remedial action | $660 | $690 | $30 |
Any other ground water remedial action | $770 | $690 | ($80) |